Voters in ten states decided 41 local ballot measures on data centers on November 3, the largest wave of such votes on record. This post tracks every one of them, plus the six decided earlier this year, the three still to come, and the recall elections the data center fights have produced, with an interactive map and results by state.
At least 50 local ballot measures on data centers in 13 states this year, 41 of them on November 3, plus the recalls they set off. Results as called by Wednesday morning.
Wednesday, November 4, 2026
The top line
38 of the 41 data center measures on Tuesday’s ballot had been called by Wednesday morning. Voters chose to limit data center development in 37 of them and to allow or support it in one. Three had not been reported.
Voters in 13 states faced at least 50 local ballot measures on data centers this year, according to Ballotpedia’s count. Forty-one of the 50 were on the November 3 ballot, in 10 states. Six were decided earlier in the year, and every one of the six went against data center development. Three more come in December.
No state had a statewide data center measure on the ballot. The one that was filed, a proposed Ohio constitutional amendment to ban data centers above 25 megawatts, did not collect its 413,487 signatures by the July 1 deadline. Its backers say they are aiming for November 2027. A Massachusetts initiative filed in August would need two-thirds voter approval and utility and water certifications before any local data center permit. If it clears review and signatures, it would appear in November 2028.
This post covers every measure we could find: what each one does, how it reached the ballot, and the result. Counts are as of Wednesday morning and will move as the last measures are called. Recall elections tied to data center decisions are at the end.
What was on the ballot
Of the 41 measures on November 3, a yes vote limited or conditioned data center development in 28 and allowed or supported it in 13.
Most of these measures came from residents, not councils. In Ballotpedia’s September count, 31 of 38 measures had qualified through citizen petitions and seven had been referred by a local governing body. The measures fall into four groups:
In the tables below, “Yes limits” means a yes vote restricts, pauses, or adds conditions to data center development. “Yes favors” means a yes vote allows a project or tells officials to support one. The outcome column records which way the result cut, regardless of how the question was worded.
Ohio
Ohio had 21 of the 50 measures, in 18 cities, villages, and townships. Voters went against data center development in all 19 that have been counted. Eleven bans passed, Perry’s financial guarantee rule and Grove City’s voter approval rule passed, Monroeville’s advisory question failed, Ashville’s EdgeConneX deal was repealed, and all four Wilmington rezonings were rejected by 80 to 20. The two Adams County township zoning votes had not been reported.
Ohio had more data center ballot measures than the next four states combined. Eleven of the 21 were bans, most of them citizen initiatives that amend a city or village charter to prohibit data centers above 25 megawatts. Wilmington alone had four referendums, each on a separate rezoning from Rural Residential to Light Industrial. Ashville voted on a term summary for negotiations with EdgeConneX. Two Adams County townships voted on whether to adopt zoning in their unincorporated areas, which would give them a say over land use, data centers included.
The Ohio measures share a background: the Ohio Capital Journal counts at least 138 municipalities and townships with data center moratoriums and 23 communities that have effectively banned them, against 257 data centers in the state. The statewide ban that missed this year’s ballot is aimed at 2027.
Every Ohio measure, by jurisdiction
| Jurisdiction | Measure | A yes vote | Result | Outcome |
|---|---|---|---|---|
| Ashville Pickaway County |
Data center development term summary referendum | Yes favorsUpholds the village's term summary guiding negotiations with EdgeConneX on two proposed data centers | Defeated 18% yes, 82% no |
Limits development |
| Conneaut Ashtabula County |
Issue 10: prohibit data centers over 25 megawatts | Yes limitsAmends the charter to prohibit data centers with aggregate demand or peak load above 25 megawatts | Approved 65% yes, 35% no |
Limits development |
| Defiance Defiance County |
Prohibit data center construction initiative | Yes limitsProhibits construction of data centers with aggregate demand or peak load above 25 megawatts | Approved 65% yes, 35% no |
Limits development |
| Granville Licking County |
Prohibit data center construction initiative | Yes limitsProhibits construction of data centers in the village | Approved 82% yes, 18% no |
Limits development |
| Grove City Franklin County |
Issue 28: voter approval for large developments | Yes limitsRequires voter approval for developments on 50 or more contiguous acres, with peak demand above 20 megawatts, or using more than 500,000 gallons of water a day | Approved 55% yes, 45% no |
Limits development |
| Hubbard Trumbull County |
Prohibit data centers initiative | Yes limitsProhibits data centers within city limits | Approved 77% yes, 23% no |
Limits development |
| Monroe Township Adams County |
Township zoning initiative | Yes limitsEstablishes zoning regulations in the township's unincorporated areas | ||
| Monroeville Huron County |
Allow data center development advisory question | Yes favorsAdvises village officials to allow data center development within village limits | Defeated 13% yes, 87% no |
Limits development |
| Oregon Lucas County |
Issue 25: prohibit data centers over 25 megawatts | Yes limitsProhibits construction of data centers with aggregate demand or peak load above 25 megawatts | Approved 60% yes, 40% no |
Limits development |
| Pataskala Licking County |
Prohibit data centers initiative | Yes limitsProhibits construction of large-scale data centers | Approved 74% yes, 26% no |
Limits development |
| Perry Lake County |
Issue 16: financial guarantees for hyperscale tax incentives | Yes limitsRequires hyperscale data center developers seeking special tax incentives to provide financial guarantees | Approved 87% yes, 13% no |
Limits development |
| Piqua Miami County |
Prohibit data center construction charter amendment | Yes limitsAmends the city charter to prohibit construction of a data center in the city | Approved 67% yes, 33% no |
Limits development |
| Sprigg Township Adams County |
Township zoning initiative | Yes limitsEstablishes zoning regulations in the township's unincorporated areas | ||
| Sunbury Delaware County |
Prohibit construction of data centers initiative | Yes limitsProhibits construction of data centers with aggregate demand or peak load above 25 megawatts | Approved 79% yes, 21% no |
Limits development |
| Trenton Butler County |
Issue 17: prohibit data centers | Yes limitsProhibits construction of large-scale data centers | Approved 80% yes, 20% no |
Limits development |
| Upper Sandusky Wyandot County |
Prohibit data center construction charter amendment | Yes limitsAmends the city charter to prohibit construction of a data center | Approved 77% yes, 23% no |
Limits development |
| Urbana Champaign County |
Prohibit construction of data centers initiative | Yes limitsProhibits construction of data centers within city limits | Approved 77% yes, 23% no |
Limits development |
| Wilmington Clinton County |
1957 SR 730 rezoning referendum | Yes favorsUpholds the rezoning of 65 acres from Rural Residential to Light Industrial | Defeated 20% yes, 80% no |
Limits development |
| McGuinn Road rezoning referendum | Yes favorsUpholds the rezoning of 191 acres from Rural Residential to Light Industrial | Defeated 20% yes, 80% no |
Limits development | |
| SR 730 rezoning referendum | Yes favorsUpholds the rezoning of 119 acres from Rural Residential to Light Industrial | Defeated 20% yes, 80% no |
Limits development | |
| US 68 South rezoning referendum | Yes favorsUpholds the rezoning of 170 acres from Rural Residential to Light Industrial | Defeated 20% yes, 80% no |
Limits development |
Illinois
Illinois had 7 measures, all advisory. All seven went against data centers. The four Madison County townships and Joliet Township said no to permitting them, by 74 to 83 percent. Bloomington backed a moratorium with 78 percent and Morgan County backed restrictions with 88 percent.
Four of the seven were in Madison County, across the river from St. Louis, where Chouteau, Granite City, Nameoki, and Venice townships asked voters whether officials should permit new data centers. Joliet asked the same question about artificial intelligence data centers. Bloomington and Morgan County asked the opposite: whether to impose a moratorium or restrictions. None of the seven binds anyone. They matter because councils and county boards tend to cite them.
Every Illinois measure
| Jurisdiction | Measure | A yes vote | Result | Outcome |
|---|---|---|---|---|
| Bloomington McLean County |
Data center moratorium advisory question | Yes limitsAdvises the city to impose a moratorium on large-scale data centers | Approved 78% yes, 22% no |
Limits development |
| Chouteau Township Madison County |
Permit data centers advisory question | Yes favorsAdvises officials to permit construction and operation of new data centers in the township | Defeated 17% yes, 83% no |
Limits development |
| Granite City Township Madison County |
Permit data centers advisory question | Yes favorsAdvises officials to permit construction and operation of new data centers in the township | Defeated 26% yes, 74% no |
Limits development |
| Joliet Will County |
AI data center construction advisory question | Yes favorsAdvises the city to approve construction of artificial intelligence data centers | Defeated 21% yes, 79% no |
Limits development |
| Morgan County Morgan County |
Data center restrictions advisory question | Yes limitsAdvises the county to impose restrictions on building and operating data centers | Approved 88% yes, 12% no |
Limits development |
| Nameoki Township Madison County |
Permit data centers advisory question | Yes favorsAdvises officials to permit construction and operation of new data centers in the township | Defeated 22% yes, 78% no |
Limits development |
| Venice Township Madison County |
Permit data centers advisory question | Yes favorsAdvises officials to permit construction and operation of new data centers in the township | Defeated 24% yes, 76% no |
Limits development |
Everywhere else on November 3
Thirteen more measures in 8 states: California, Florida, Kansas, Maine, Nevada, New Jersey, North Dakota, Wisconsin. Twelve of the thirteen have been counted, and eleven went against data center development. All three Kansas bans passed, all four Maine votes passed, and the Alhambra and Edgewater bans passed with more than three quarters of the vote. Janesville now requires a public vote on the GM site. Downe Township voters said no to an advisory question in favor. The one exception was Harwood, North Dakota, where voters rejected an added review requirement for industrial projects, 75 to 25. Boulder City, Nevada is still counting mail ballots.
Maine had four town votes, three of them moratoriums. Kansas had three citizen initiatives to ban high-impact data centers, including one in El Dorado that also covers battery storage. Alhambra, California and Edgewater, Florida voted on outright bans. Janesville, Wisconsin voted on whether any development of the former General Motors site costing more than $450 million must go to voters. Boulder City, Nevada had the one council-referred question that would open land to data centers, in the Eldorado Valley Transfer Area. Downe Township, New Jersey asked an advisory question in favor.
Every measure, by state
| State | Jurisdiction | Measure | A yes vote | Result | Outcome |
|---|---|---|---|---|---|
| California | Alhambra Los Angeles County |
Measure DB: prohibit data centers | Yes limitsProhibits data centers in the city | Approved 82% yes, 18% no |
Limits development |
| Florida | Edgewater Volusia County |
Prohibit new data centers charter amendment | Yes limitsProhibits new data centers from being approved, built, expanded, or operated in the city | Approved 77% yes, 23% no |
Limits development |
| Kansas | El Dorado Butler County |
Prohibit data centers and battery storage initiative | Yes limitsProhibits construction of high-impact data centers and Type 2 and Type 3 battery energy storage systems | Approved 71% yes, 29% no |
Limits development |
| Emporia Lyon County |
Prohibit high-impact data centers initiative | Yes limitsProhibits construction of high-impact data centers in the city | Approved 60% yes, 40% no |
Limits development | |
| Ottawa Franklin County |
Question 2: prohibit data centers over 25 megawatts | Yes limitsProhibits construction of data centers using more than 25 megawatts of power | Approved 69% yes, 31% no |
Limits development | |
| Maine | North Berwick York County |
Question 2: prohibit data centers | Yes limitsProhibits data centers of 25,000 square feet or more | Approved 78% yes, 22% no |
Limits development |
| Peru Oxford County |
Article 2: data center moratorium | Yes limitsAdopts a 180-day moratorium on data center development and permitting | Approved 76% yes, 24% no |
Limits development | |
| Wells York County |
Article 5: data center moratorium | Yes limitsEstablishes a 180-day moratorium on data center development | Approved 82% yes, 18% no |
Limits development | |
| Wiscasset Lincoln County |
Question 2: data center moratorium | Yes limitsEstablishes a six-month moratorium on applications for new or expanded data centers | Approved 66% yes, 34% no |
Limits development | |
| Nevada | Boulder City Clark County |
Question 1: allow data centers in the Eldorado Valley Transfer Area | Yes favorsAllows data centers within the Eldorado Valley Transfer Area | ||
| New Jersey | Downe Township Cumberland County |
Data centers advisory question | Yes favorsAdvises support for data centers in the township | Defeated 13% yes, 87% no |
Limits development |
| North Dakota | Harwood Cass County |
Industrial development review initiative | Yes limitsRequires additional review before the city approves industrial developments, including data centers | Defeated 25% yes, 75% no |
Favors development |
| Wisconsin | Janesville Rock County |
Voter approval for the GM/JATCO site initiative | Yes limitsRequires voter approval before the city leases, sells, transfers, or approves development of the former GM/JATCO site if project costs exceed $450 million | Approved 63% yes, 37% no |
Limits development |
Decided earlier this year
Six measures were decided between March and September. All six went against data center development, by margins of 66 to 90 percent.
Two New Hampshire towns voted at their March and September town meetings. Monterey Park, California passed a ban in June with 88 percent. Augusta Township, Michigan voters rejected a rezoning for a proposed data center with 90 percent voting no. Wrightstown, Wisconsin voters said no, 87 to 13, to committing public resources to a large-scale data center. Port Washington, Wisconsin now requires a vote before the city creates a tax incremental district above $10 million.
| State | Jurisdiction | Measure | A yes vote | Result | Outcome |
|---|---|---|---|---|---|
| California | Monterey Park Los Angeles County |
Measure NDC: prohibit data centers June 2, 2026 |
Yes limitsAmends the city's land use element to prohibit data centers | Approved 88% yes, 12% no |
Limits development |
| Michigan | Augusta Township Washtenaw County |
Rezoning for a data center referendum August 4, 2026 |
Yes favorsUpholds Ordinance 2025-02, rezoning properties from agricultural residential to general industrial for a proposed data center | Defeated 10% yes, 90% no |
Limits development |
| New Hampshire | Canterbury Merrimack County |
Article 4: prohibit data centers March 10, 2026 |
Yes limitsProhibits data centers within the town | Approved 84% yes, 16% no |
Limits development |
| Nottingham Rockingham County |
Data center permitting moratorium September 8, 2026 |
Yes limitsBars the town from accepting data center permit applications for 12 months | Approved 90% yes, 10% no |
Limits development | |
| Wisconsin | Port Washington Ozaukee County |
Voter approval for tax incremental districts over $10 million April 7, 2026 |
Yes limitsRequires voter approval before the city creates or approves a tax incremental district with base value or project costs above $10 million | Approved 66% yes, 34% no |
Limits development |
| Wrightstown Brown County |
Data center development advisory question August 8, 2026 |
Yes favorsAdvises the village board to commit public resources or infrastructure to a large-scale data center | Defeated 13% yes, 87% no |
Limits development |
Still to come
Clarksville, Arkansas votes December 1 on two bond authorizations for named data center projects, one for up to $50 billion in industrial development bonds for a Hatchbo LLC site and one for up to $5 billion for SF ARK1 LLC. Both come with payment-in-lieu-of-taxes agreements. Mandan, North Dakota votes December 15 on a 25-megawatt ban.
| State | Jurisdiction | Measure | A yes vote | Result | Outcome |
|---|---|---|---|---|---|
| Arkansas | Clarksville Johnson County |
Hatchbo data center bond referendum December 1, 2026 |
Yes favorsUpholds Ordinance 26-1007, authorizing up to $50 billion in industrial development bonds for a Hatchbo LLC data center and a payment-in-lieu-of-taxes agreement | ||
| Clarksville Johnson County |
SF ARK1 data center bond referendum December 1, 2026 |
Yes favorsUpholds Ordinance 26-1008, authorizing up to $5 billion in bonds for SF ARK1 LLC land acquisition and a payment-in-lieu-of-taxes agreement | |||
| North Dakota | Mandan Morton County |
Measure 1: prohibit data centers over 25 megawatts December 15, 2026 |
Yes limitsProhibits data centers with anticipated electrical capacity or demand of 25 megawatts or more |
Measures that did not make the ballot
The 50 measures are the ones that survived. Ballotpedia tracked at least 17 local proposals in 13 states that did not reach a ballot, plus the Ohio statewide amendment. The reasons are a guide to where the next fights will be: signature counts, deadlines, court rulings that a zoning or incentive decision is administrative and not subject to referendum, and councils that repealed an ordinance rather than face a vote.
| Where | Proposed measure | What happened |
|---|---|---|
| Ohio (statewide) | Prohibition of Data Center Construction Amendment, a constitutional ban on data centers above 25 megawatts | Backers needed 413,487 valid signatures by July 1. On June 17 they said they would not make it and are aiming for the November 2027 ballot. |
| Marana, Arizona | Referendum on a data center approval | The clerk rejected about 2,800 signatures as invalid; a Pima County judge upheld the rejection on May 1. |
| Coweta County, Georgia | Local campaign | A campaign launched; no measure reached the ballot. |
| Edgerton, Kansas | Referendum on a data center approval | Signatures were verified, but the city sued to block it. A judge dismissed the city's suit; a separate suit was pending as of September. |
| Frederick County, Maryland | Referendum on a county zoning plan for data centers | Signatures were sufficient, but the Maryland Supreme Court ruled on June 30 that the referendum could not go on the ballot. |
| Mason, Michigan | Referendum on a data center ordinance | The city council repealed the ordinance instead of sending it to voters. |
| Independence and Joplin, Missouri | Referendums on data center approvals | In Independence, a judge ruled the ordinance was not subject to referendum. In Joplin, about 2,800 signatures were submitted of about 5,000 required. |
| Butte-Silver Bow and Yellowstone County, Montana | Referendums on data center approvals | In Butte-Silver Bow, officials found the signature deadline had passed. In Yellowstone County, a judge ruled on August 15 that the July 13 deadline had passed. |
| Massena, New York | Town measure | The town board did not authorize the measure. |
| Boulder City, Nevada | Citizen initiative | Backers collected 1,284 of 1,541 required signatures and did not submit by the deadline. A separate council-referred question is on the November 3 ballot. |
| Claremore, Oklahoma | Referendum petition | Petitions were declared invalid because they were not filed with the city clerk before signature gathering. |
| Lubbock and Taylor, Texas | Citizen initiatives | Lubbock's backers dropped their initiative after the council began a 90-day moratorium process. Taylor's was ruled unavailable because Texas law routes zoning changes through commission review and public hearings. |
| Box Elder County, Utah | Referendum on county resolutions | The county attorney rejected it on May 28 as administrative rather than legislative; opponents appealed to district court. |
| Cheyenne, Wyoming | Referendum petition | Proponents reported about 3,200 signatures against a 2,739 requirement; the clerk was still verifying at last report. |
Recalls
Data center decisions have also produced recall elections. Ballotpedia counted 42 recall efforts against 80 local officials over data center projects through early October. On Tuesday, voters removed a council member in Mason, Michigan, the mayor of Yukon, Oklahoma, the mayor of Urbana, Ohio, and three Piqua, Ohio commissioners. San Angelo, Texas had not reported.
Recalls are the other half of this story. Where residents cannot put a project on the ballot, some have put the officials who approved it on the ballot instead. Independence, Missouri recalled a council member on September 1 over a 90 percent tax abatement for a Nebius data center. The Town of Turtle, Wisconsin removed its longtime chairman on October 6 after a dispute that included a $1 billion Panattoni data center campus. On Tuesday the pattern held. In Mason, Michigan, the recalled council member lost to a challenger backed by the anti-data center group, and that group’s slate won all four regular council seats. In Yukon, Oklahoma, the mayor lost his council seat with more than 80 percent voting for the challenger. Piqua and Urbana, Ohio removed officials the same night they banned data centers.
| Where | Official | The decision at issue | Result |
|---|---|---|---|
| Independence, Missouri | Councilman John Perkins (First District) September 1, 2026 |
Voted to approve a 90 percent tax abatement for a Nebius data center of 2.1 million square feet in the Little Blue Valley | Recalled |
| Town of Turtle, Wisconsin | Town Chairman Roger Anclam October 6, 2026 |
Recall followed disputes that included a proposed $1 billion data center campus by Panattoni Development | Recalled. Donna Redner won, 400 votes (63 percent) to 232 (27 percent) |
| Mason, Michigan | Council Member Elaine Ferris November 3, 2026 |
Council actions on a proposed hyperscale campus of about $1 billion on 400 acres in neighboring Vevay Township, which sought annexation into Mason. A second petition against Mayor Russ Whipple is headed for May 2027. | Recalled. Challenger Pam Oliver won the seat, 1,941 votes (58 percent) to 933 for Ferris and 447 for Daniel Giganti |
| Piqua, Ohio | Three city commissioners November 3, 2026 |
Commission votes on a data center project, the same dispute behind Piqua's charter amendment | All three recalled, with more than 70 percent voting to remove (unofficial) |
| Urbana, Ohio | Mayor Bill Bean November 3, 2026 |
City actions on a data center project, the same dispute behind Urbana's ban initiative | Recalled |
| Yukon, Oklahoma | Mayor Brian Pillmore (Ward 3) November 3, 2026 |
City land sale near State Highway 66 and Frisco Road to Belt Line Energy for a data center. Vice Mayor Jeff Wootton, also named in the petition, resigned in June. | Recalled. Challenger Joe Phillips won the seat with more than 80 percent |
| San Angelo, Texas | District 3 Council Member Harry Thomas November 3, 2026 |
Voted for the rezoning of about 350 acres of city land for a Skybox Datacenters campus. Petitions against the mayor and a second council member fell short of the signature requirement. |
Latest News
Photo credit: iStock.com/Jehan-Jehan Democrats won the House and the Senate, picked up five governorships, and flipped seven state legislative chambers on Tuesday. Here is where every Senate, governor, and state legislative race stood as of [...]
Photo credit: iStock.com/Rawpixel Election night will tell you who won the race, but it doesn’t tell you who will chair the committee that handles your bill, who will run the agency that regulates your industry, [...]
Photo credit: iStock.com/gorodenkoff On August 18, 2026, Governor Josh Shapiro signed Executive Order 2026-05, a new Pennsylvania data center executive order addressing the growth of data center development across the Commonwealth. The order begins implementing [...]
Photo credit: iStock.com/Techa Tungateja As Artificial intelligence continues to evolve and skepticism about its use grows, state lawmakers across the country are preparing for its integration into public school systems. Growing disconcertion surrounding AI use [...]






Stay In Touch